Search
"CPWD is observing Vigilance Awareness Week-2023" from 30th October 2023 to 5th November 2023. Three Month campaign (16th August 2023 - 15th Novenber 2023). The theme of VAW-2023 is "Say no to Courruption; Commit to the nation (भ्रष्टाचार का विरोध करे; राष्ट्र के प्रति समर्पित रहें)" | The Central Government Employees Welfare Housing Organisation (CGEWHO) has launched a long-awaited housing scheme in Kolkata (W.B.) and Visakhapatnam (AP). Interested Eligible Central Government Employees may apply till 6th October, 2023. For more information kindly visit
For Visakhapatnam Housing Project
&
For Kolkata Housing Project
|
Interview of Director General, CPWD on Doordarshan
|
Click Here to View New CPWD Website
|
Souvenir of 5th International Conference on “Construction Arbitration - The Indian and International Perspective
| PPTs on
'Interior Design of Buildings'
,
'Smart Thermal Solar Panel'
and
'Geothermal exchange and Net Zero Buildings'
are uploaded in the website | All office heads may please fill network information on “Internet Network Information Module” in PIMS on Priority.
Click here to view help file.
|
Implementation of Transfer, Posting, Relieving and Joining in ERP System has been made live, All are requested to mandatorily use this module.
Home
About us
Organisation
Profile
Office
Citizen
Citizen Charter
Maintenance Charter
Right to Information
Citizen Corner
Recognized Service Associations/unions
Human Resource
Employees
Recruitment Rules
Appreciations & Awards
National Career Service Portal
Projects
Major Projects
Workload
Cost Indices
Energy Efficiency Measures
Budget and Expenditure
Health Infrastructure Projects
Renewable Energy
Integrity Pact and IEMs
Contractors
Contractors' Enlistment Management System
List of Contractors
Circulars Related to Enlistment/Debarment
Enlistment Rules
Survey of Procurement Process by World Bank
Documents
CPWD Publications
Circulars
PPTs
Videos
DGs' Messages
Archives
CPWD Day
CCEA Decisions
Azadi Ka Amrit Mahotsav
Vigilance
Contact Us
Contact Us
Telephone Directory
Feedback
You are here :
Home
>
Projects
>
Health Infrastructure Projects
About Us
Health Infrastructure Projects
Bimonthly Progress Report on PMSSY projects of more than Rs. 10 crore with CPWD
Amount in Rs crore
S No
Approved DPR cost
(AA & ES)
Approved contract value
Date of Award
Date of completion as per current progress
Status of work
Amount allocated
Hindrances
Completion chart
Target date of completion
1
Name of the project:
Up gradation of Govt. Medical College & Hospital under Phase-III of PMSSY at Akola Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room
Zone
WZ II
52.00
48.00
10.09.2016
09.01.2018
31.10.2020
work is in progress. Civil work is 99.5% complete and Electrical work 99.5% complete. Overall work is 99.5% complete.
55.35
1. During 1st week of November, 2017 the representative of M/s HITES ( HLL Infratech services Ltd ) Noida Inspected the ongoing construction works and suggested following major changes. 2. Increase of 5th floor height from 3.90 m to 4.70 m since Modular Operation Theatres (MOTs) has to be installed in this floor. The concept of Modular OTs was not under scope of original scope of work of agreement. This resulted in changes of floor height and change in sizes of OTs in fifth floor. Providing ad
2
Name of the project:
Construction of Superspeciality Hospital at Patliputra Medical College, Dhanbad under PMSSY Phase-III
Zone
EZ IV
857100.00
500800.00
27.08.2016
26.12.2017
26.12.2017
Block-A 1st & 2nd floor roof slab has been casted. Block-B 1st floor roof slab has been casted and column work is in progress for casting of 2nd floor reinforcement binding work is in progress. Bloc
220700.00
Initially site was hindered by local public & heavy Rainfall causing delay in foundation work .Also approach of site was totally blocked by durga puja committee during puja festival ( 2 month)
3
Name of the project:
Upgradation of SVN Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal.
Zone
74.36
48.47
12.09.2016
31.10.2019
11.01.2018
Work is in progress and 83% completed.
58.00
Agency submitted proposal for rescheduling of milestones. Comments / Clarifications sought by EE from agency - yet to be received.
4
Name of the project:
Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum
Zone
150.00
44.00
12.02.2018
31.03.2020
29.08.2019
Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuteering in progress
69.00
Initial delay in handing over site & finalisation of drawings
5
Name of the project:
Up-gradation of Jawahar Lal Nehru Medical College & Hospital, Bhagalpur under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.
Zone
REGION
109.00
101.00
17.07.2018
16.02.2020
30.03.2023
Completed . Testing & commissioning of Civil & E&M services are being checked. Minor touch up work is going on in tune with HITES work.
103.00
Work delayed due to 2nd call of tender. First call of tender was done on 14.12.2017 and 2nd call on 14.05.2018. Conceptual drawing approved on 07/12/2018. Non- receipt of statutory approval upto 02/2019. Work also slowed down during Lok sabha General Election 2019 due to non availability/scarcity of materials. Excessive rainfall and water logging at site in June, July 2019. First floor Slab casting stopped due to unprecedented rain and water logging in the last week of
6
Name of the project:
Up gradation of Shri Vasantrao Naik Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room
Zone
WZ II
52.00
48.00
12.09.2016
11.01.2018
30.11.2020
Works are in progress. Civil work is 99% complete and Electrical work is 85% complete. Overall work is 97% complete.
58.00
1. Delay due to existing LT/HT poles passing through the location of Hospital Building. 2. Delay due to existing water supply line passing the foundation of Middle Wing of Building. 3. Revision of floor drawings after the inspection of HITES in November 2017 and final drawing issued on 16th January 2018. Major issue was to increase the height of 5th floor height from 3.9 m to 4.7 m and various additional requirements. 4. Delay in taking up the UG sump & Substation building due to existing W/S
7
Name of the project:
Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum
Zone
150.00
44.00
12.02.2018
31.03.2020
29.08.2019
Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuteering in progress
69.00
Initial delay in handing over site & finalisation of drawings
8
Name of the project:
C/o super speciality Hospital, Bilaspur under PMSSY phase IV on EPC
Zone
REGION
109.00
98.62
09.08.2018
08.05.2020
23.02.2021
1) RCC frame structure upto seventh Floor slab,50% 8th floor slab is completed. 2)Brick work upto 5th floor, service building first floor column, ug tank raft foundation, ramp, road work is going on.
64.21
There is initial delay due to shifting of site location. 2)Delay in demarcation of land by the state government officials due to which Process of obtaining different statuary Approvals delayed. 3)Due to the delay in execution of work as client department demands full basement instead of basement in 25 % of area as mentioned in the agreement. 4)Due to the delay in basement, foundation work falls in rainy season and backfilling works delayed as backfilling soil was not available due to rainy
9
Name of the project:
C/O AIIMS AT AWANTIPORA (KASHMIR) (J&K)
Zone
CE CUM ED(AIIMS AWANTIPURA)
15770000000.00
16493752000.00
07.11.2020
22.05.2024
22.05.2024
Work has been awarded with stipulated date of start and completion as 23.11.2020 and 22.05.2024 respectively (Period of construction 42 Months).The Contractor (M/s NCC Ltd) has started mobilisation o
420000000.00
Expeditious completion of utilities by state government (Road, Water, Electricity), Multiple point access to site, Allotment of balance 34 acre land, Security for construction at site are required to take up the project in a time bound manner. Also, deposition of funds by MoHFW is required immediately.
10
Name of the project:
Upgradation of Patna Medical College and Hospital , Patna under PMSSY (Phase-IV)
Zone
CE(PATNA)
118.00
84.00
07.03.2019
30.11.2021
06.11.2020
Foundation work in progress.
36.00
Non-handing over of hindrance free site, Local body submission and approval got delayed due to non-availability of land records, Land possession certificate not yet received, Delay in receipt of EIA clearance, Land for multilevel parking not yet handed over. Delay due to Cobid pandemic.
11
Name of the project:
UP-GRADATION OF PATNA MEDICAL COLLEGE & HOSPITAL UNDER PMSSY, PHASE-IV
Zone
CE(PATNA)
119.00
85.00
07.03.2019
31.05.2022
06.11.2020
1. Initial Pile Load test Completed. 2. Shifting of tree and transformer completed. 3. Land Document (Land Possession Certificate) yet not received from PMCH, Patna, The land record and detail of due
36.00
1. Tender Invited on 18.12.2017(first call) and due to unavailability of land tender was cancelled on 03.04.2018 after extending the date of opening four times. 2. The tender re-invited on 18.07.2018 with stipulated date of opening on 09.08.2018. 3. Award of work got delayed by 5 months due to delay in handing over of land by PMCH on 13.02.2019 vide letter no 824. 4.The delay in vacation old structure/quarter at site of main Building. 5. Central dispensary yet to be vacated/demolished. 6.
12
Name of the project:
Up-gradation of Anugrah Narayan Magadh Medical College & Hospital, Gaya under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.
Zone
CE CUM ED(BODHGAYA PROJECT ZONE)
108.00
90.32
13.04.2018
30.09.2020
24.04.2020
i.)Service Block:- Structural Work Completed. Brick & Plaster Work was in Progress. ii) Main Building :- Terrace Level Casting was in progress. Brick & Plaster work was in Progress.
47.11
Due to following reasons the work has been delayed:( A). Initial Hindrance for Starting the work Smoothly:-1.Due to land document not hand over by ANMMCH, Planning and finalization of Lay out was delayed.2.Due to conceptual drawing not approved by Ministry of Health and Family Welfare, Planning and finalisation of Lay out was delayed.3.Due to pending NOC for Dismantling of Qtrs and Hostel from Building Construction Deptt, Gaya, foundation work was delayed.4.Due to pending shifting of Overhead tr
13
Name of the project:
Upgradation of IGIMS Patna under PMSSY (Phase-VB)
Zone
CE(PATNA)
119.00
80.00
22.11.2020
21.05.2022
28.05.2022
EPC Contract, Planning work in progress, All input on architectural drawings received from client on 13-01-2021, Approval of Structure DBR conveyed, Approval of MEP DBR is in progress.
12.00
Environmental Clearance is in process, next meeting of SEAC likely in mid february 2021.
14
Name of the project:
CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT BILASPUR UNDER PMSSY (PHASE-IV).
Zone
REGION
109.00
86.00
31.08.2018
31.12.2022
30.04.2020
Civil: - 92.25% Electrical: -75% Hospital Building (Basement +G+10) Storied- Flooring 96%completed (except basement), B/W,internal Plaster, Sanitary pipeline, Internal Water supply line-96% com
90.00
1) There is initial delay due to shifting of site location. 2) Delay in demarcation of land,P2 form,nazri naksha nakal naksha by the state government officials due to which Process of obtaining different statuary Approvals delayed. 3)Due to the delay in execution of work as client department demands full basement instead of basement in 25 % of area as mentioned in the agreement. 4)Due to the delay in basement, foundation work falls in rainy season and backfilling works delayed as backfilli
15
Name of the project:
Up-gradation of Agartala Government Medical College, Tripura under PMSSY Phase-III at Agartala. [Sub Head: Construction of Super Specialty Block to house 07 Super specialty facilities with 170 beds including internal & external water supply, sanitary installations, drainage, electrical installations, air-conditioning, development etc
Zone
1145400000.00
1145400000.00
29.03.2017
14.10.2019
14.10.2019
1. Site Clearance, plant and machinery set up in progress. Barricading with GI sheet in from of building has been completed.2. Pile test design & retaining wall design submitted by the contractor. Des
100000000.00
There is no delay as of now for design activities. However, There are few unauthorized hutments within the site of construction. Matter has been taken up with state authorities for their removal.
16
Name of the project:
CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT PATLIPUTRA MEDICAL COLLEGE UNDER PMSSY PHASE-III AT DHANBAD, JHARKHAND
Zone
EZ IV
85.71
50.08
15.07.2016
26.12.2017
14.01.2018
Physical Progress-37%.Block-A-2nd floor slab has been casted, 3rd floor column work is in progress.Block-B 1st floor casted & reinforcement binding work is in progress.Block-C 3rd floor roof slab cast
22.07
Initially work start delayed due to heavy rain fall and subsequent flooding of work site being a slopy terrain.
17
Name of the project:
Upgradation of Baba Raghav Das Medical College at Gorakhpur under PMSSY Phase-3.
Zone
69.87
43.97
19.05.2016
18.10.2017
31.01.2018
RCC works in progress for terrace slab, brickwork in progress at GF, 1st Floor & 2nd floor.Ac ducting & Fire Fighting material arrived at site. Targets Physical -55% Achieved 52%, Financial 47% Achiev
29.00
Initial delay of 3 months in removal of encroachment from site by the college. Some encroachment still exists at rear side road location. Limited availability of sand & aggregates in UP.
18
Name of the project:
Upgradation of Lala Lajpat Rai Memorial Medical College at Meerut under PMSSY Phase-3.
Zone
NZ II
69.99
47.49
11.06.2016
10.11.2017
10.11.2017
RCC work up to terrace and brick work completed.Plastering, tiling work, HVAC & fire fighting work in progress. Cumulative targets Physical-74% Achieved-66% Financial-59% Achieved-55%
24.98
Progress (Activities like RCC, brickwork, plastering etc) got slowed down during April to Middle of June due to non-availability of sand/aggregates in U.P
19
Name of the project:
Trauma Centre and Emergency Medical Block at Malda Medical College and Hospital at Malda under PMSSY Phase-3.
Zone
EZ I
61.39
44.96
17.12.2016
16.08.2018
31.12.2018
The work is yet to start as site has not been made available by the hospital administration.
6.13
Site not clear. Nurses hostel existing on the site is being demolished by the college.
20
Name of the project:
Up-gradation of B.S.Medical College, Bankura under PMSSY, Phase-III
Zone
EZ III
79.00
54.50
05.08.2016
31.03.2018
31.03.2018
Shuttering of 4th slab in progress.
41.00
1.Site handed over by the Client on 05.09.2016 while the stipulated date of start is 20.08.2016. 2.Exact locations of medical equipments not received from HITES so far
21
Name of the project:
Upgradation of Government Medical College & Hospital at Akola under PMSSY Phase-3.
Zone
74.75
48.19
10.09.2016
31.10.2019
09.01.2018
Right block-1st floor slab & beam reinforcement placing in progress.Left block- 3rd floor columns in progress. AAC block masonry completed at GF. Work is 96% completed
48.00
1st & 2nd Mile stones shifted by 75 days. The agency agreed to cover up this delay of 75 days by the end of 3rd milestone. Hence as an date target date is same as stipulated date of completion.
Completion chart